Overview

The company needs to monitor fulfillment of subcontracting purchase orders and subcontractor's raw materials.

The process ensures that raw materials are provided on time, and finished products are entirely available on a certain date, and the subcontractor stock is picked up in full.

In case of delays, the company needs to regularly send reminders and notifications.

As a result of the process, external subcontracting transactions are followed up.

Follow up external subcontracting transactions flowchart

Follow up external subcontracting transactions

(v.0)

Loading diagram...

How to monitor subcontractor stock fill-up with raw materials

Context report

Paths

PathManufacturing → Subcontracting → Subcontracting purchase orders
In-app link EN code

e1cib/list/Document.SubcontractOrder2_5

In-app link RU code

e1cib/list/Документ.ЗаказПереработчику2_5

1. Go to Manufacturing and then click Subcontracting purchase orders under Subcontracting.

2. Select an order, click Reports, and select Fulfillment status.

3. In the Fulfillment status report, in the Shipped section, review the information about the raw material delivery status.

Comprehensive report

Paths

PathManufacturing → Manufacturing reports → Subcontracting → Control of raw and consumable materials delivery to subcontractor
In-app link EN code

e1cib/data/Catalog.ReportsOptions?ref=885c0050569fc7f211ed590fbc07b706

In-app link RU code

e1cib/data/Справочник.ВариантыОтчетов?ref=811c60a44ccf99dc11eccd5ce40cc491

1. Go to Manufacturing, click Manufacturing reports, and then open the Control of raw and consumable materials delivery to subcontractor report under Subcontracting.

2. Set a period, a Company, and a Subcontractor.

3. Click Generate.

4. In the Ordered column, review the raw materials to deliver to the subcontractor.

5. In the Handed over column, review the raw materials that are already delivered to the subcontractor.

Paths

PathManufacturing → Manufacturing reports → Subcontracting → Product delivery control by subcontractor
In-app link EN code

e1cib/data/Catalog.ReportsOptions?ref=885c0050569fc7f211ed590fc21bf193

In-app link RU code

e1cib/data/Справочник.ВариантыОтчетов?ref=811c60a44ccf99dc11eccd5ce40cc492

How to monitor product manufacturing by subcontractors

1. Go to Manufacturing, click Manufacturing reports, and then open the Product delivery control by subcontractor report under Subcontracting.

2. Set a period, a Company, and a Subcontractor.

3. Click Generate.

4. In the Ordered column under Receipts from subcontractors, review the products to be manufactured by the subcontractor.

5. In the Registered column under Receipts from subcontractors, review the products manufactured and received by the subcontractor.

How to monitor pick-up of raw materials from subcontractor stock

Subcontracting stock

Paths

PathManufacturing → Manufacturing reports → Subcontracting → External subcontracting stock
In-app link EN code

e1cib/data/Catalog.ReportsOptions?ref=885c0050569fc7f211ed590fc21bf225

In-app link RU code

e1cib/data/Справочник.ВариантыОтчетов?ref=811c60a44ccf99dc11eccd5ce40cc49d

1. Go to Manufacturing, click Manufacturing reports, and then open the External subcontracting stock report under Subcontracting.

2. Set a period, a Company, and a Subcontractor.

3. Click Generate.

4. In the Closing balance column, review available raw materials in the subcontracting stock.

Stock returned

Paths

PathManufacturing → Manufacturing reports → Subcontracting → Goods transferred to subcontractors
In-app link EN code

e1cib/data/Catalog.ReportsOptions?ref=978834415df939ee11edf3286dcb930c

In-app link RU code

e1cib/data/Справочник.ВариантыОтчетов?ref=83f2edad5095601b11ecd0fefbb4069b

1. Go to Manufacturing, click Manufacturing reports, and then open the Goods transferred to subcontractors report under Subcontracting.

2. Set a period, a Company, and a Subcontractor.

3. Click Generate.

4. In the Transferred to warehouse column, review the raw materials returned from the subcontracting stock.

How to monitor subcontractor notification registration

1. Go to Manufacturing, click Manufacturing reports, and then open the Product delivery control by subcontractor report under Subcontracting.

2. Set a period, a Company, and a Subcontractor.

3. Click Generate.

4. In the Ordered column under Subcontracting services notifications received, review a subcontractor notification to register.

5. In the Registered column under Subcontracting services notifications received, review the registered subcontractor notification.

Paths

PathPurchasing → Purchasing reports → Vendor AR/AP → Vendor AR/AP open items
In-app link EN code

e1cib/data/Catalog.ReportsOptions?ref=810d4cedfb67459311eca6c9314b76b1

In-app link RU code

e1cib/data/Справочник.ВариантыОтчетов?ref=8e500050568b35ac11e8e193bcb573c3

How to monitor accounts payable to subcontractors

1. Go to Purchasing, click Purchasing reports, and then open the Vendor AR/AP open items report under Vendor AR/AP.

2. Set a period, a Company, and a Vendor.

3. Click Generate.

4. In the Vendor payables column, review the information about accounts payable to the subcontractor.

How to initiate issue resolution within the company

Create document-based task requests

1. Open the required document.

2. Create a Duty based on the document.

3. In the Duty field, specify a working name.

4. Assign it to the responsible user within the database.

5. Set the Priority and specify a Due date.

6. In the Subject field, describe the actions to take.

7. Start and close the document.

 