Overview
The internal demand for a specific business unit is populated with past inventory consumption statistics.
You need to check the automatically populated data, and amend it to consider the actual parameters in the planning calculations. Then you need to submit the data.
The analytics set which comes from scenario settings will guide you through this process. The analytics set can also include a warehouse and an assignment.
The forecast adjustments must be left in the comments fields. This will help you to make a root cause analysis later.
As a result of the process, the inventory consumption plan for the business unit is populated and submitted to demand planning.
Populate inventory consumption plans for business units with statistics flowchart
Paths
Path | Budgeting and planning → Budget process → My tasks |
---|---|
In-app link EN code |
e1cib/list/Task.BudgetTask
|
In-app link RU code |
e1cib/list/Задача.БюджетнаяЗадача
|
How to find and review budget tasks
1. Go to Budgeting and planning and click My budget tasks under Budget process. 2. Find the Budget task related to the budgeting process step and open it. 3. In the Budget task document, click the Additional information tab. 4. Review the time requirements in the Due date field. 5. Review the task details in the Instructions field and make sure you understand them. 6. Review the start date and time in the Start field. 7. Review the Main task and Process stage - base document fields. 8. Click the hyperlink in the middle of the form and review the input settings. 9. Click the Task action tab. 10. Click Enter plan to drill down to the entry form to fill in or the reference document. Note Hyperlinks in steps 8 and 10 appear if Plan entry is selected in the Action field.
Paths
Path | Budgeting and planning → Sales and operations plans → Inventory consumption plans |
---|---|
In-app link EN code |
e1cib/list/Document.InventoryConsumptionPlan
|
In-app link RU code |
e1cib/list/Документ.ПланВнутреннихПотреблений
|
How to populate inventory consumption plans for business units with statistics
1. Go to Master data and settings and then click Budgeting and planning under Master data and sections.
2. Select the Inventory consumption plans check box under Planning.
3. Go to Budgeting and planning and then click Inventory consumption plans under Sales and operations plans.
4. Open the Inventory consumption plan document, and then click the Main tab.
5. Fill the Scenario and the Plan profile relevant for the planning step.
6. Specify the Period.
7. Choose the Business unit (or Dispatching unit), Warehouse, or other applicable dimension, if required by the plan profile settings.
8. Click the Product categories / Goods / Manufactured products tab.
9. Click Fill in categories / goods → By default rule. The system will automatically fill the lines in accordance with the Population settings of the Plan profile. Fill in the lines manually or choose other filling options if necessary.
10. Review the information and check that the data is complete.
11. Correct the figures if necessary.
12. Specify any relevant notes, such as special requirements, in the Comment field.
13. Click and attach additional files.
14. Set the Created status and post the document.
Paths
Path | Budgeting and planning → Tools → Planning process management |
---|---|
In-app link EN code |
e1cib/app/DataProcessor.PlanningProcessManagement
|
In-app link RU code |
e1cib/app/Обработка.УправлениеПроцессомПланирования
|
How to submit inventory consumption plans for business units
1. Go to Budgeting and planning and then click Planning process management under Tools. 2. Choose the Scenario and specify the planning Period. 3. Find the Plan profile related to the process. 4. Double-click the relevant flowchart area, select the plan document, and click Set status → Submitted. The system will automatically set the Submitted status for the document.
How to complete budget tasks
1. Go to Budgeting and planning and click My budget tasks under Budget process. 2. Find the Budget task related to the process step and open it. 3. Enter the date of completion in the Completed field. 4. Click Complete and close.