You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 73 Next »

Переписать - сделать обособленное обеспечение.


Overview

The information about the requested products, quantity, and dates is captured and recorded in the order for material.

Before order confirmation, the control of goods availability to be delivered from stock is required.

Supply manager verifies whether the quantity of goods required by the order can be delivered from the warehouse on time.

During the process, the current available stock and expected goods delivery are considered.

As a result, the goods availability for supply from stock is controlled.

Control goods availability for sales from stock flowchart

Control availability of goods in stock for sales order

(v.0)

Loading diagram...


Paths

PathWarehouse and delivery → Demand fulfillment → Order supply forecast
In-app link EN code

e1cib/command/CommonCommand.OrderSupplyForecast

In-app link RU code

e1cib/command/ОбщаяКоманда.СостояниеОбеспеченияЗаказов

How to review goods availability states

1. Go to Warehouse and delivery and click Order supply forecast under Demand fulfillment.

2. Select the order list and expand its lines.

3. Review the item, the variant, the Warehouse from which these items must be supplied, the Quantity to be supplied, and the Requested supply date.

4. Review the State column, find the lines with the Supplied on warehouse state. These goods are now available in stock.

5. Find the lines with the Supplied by date state. These goods will be available by confirmed supply order. The Date of receipt is defined according to the supply order information. 

6. Find the lines with the Expected based on unconfirmed order state. These goods will be available by unconfirmed supply order. The Date of receipt is defined according to the standard lead times.

7. Find the lines with the Supply state. The supply of these goods is not initiated. The Date of receipt is defined according to the standard lead times.

8. Compare the Requested supply date with the Date of receipt.

9. Drill down to supply orders in the Receipt order column if it is required.

Note

Date of receipt value descriptions:

  • Confirmed or scheduled production date of Production order
  • Confirmed or scheduled goods receipt date of Purchase order
  • Standard Lead times of applicable Procurement strategy
  • Not defined means there is no applicable Procurement strategy

How to determine other delivery terms

1. Find the item with the latest Date of receipt. Prepare the proposal to move the order delivery date forward.

2. Prepare the proposal to split the order delivery.

3. Prepare the proposal to exclude the items that cannot be delivered on time.

How to negotiate another delivery terms

1. Inform the initiator about available delivery options.

2. Document the terms agreed.

How to update orders

1. Go to Warehouse and delivery and click Order supply forecast under Demand fulfillment.

2. Find the order and open it.

3. Make necessary changes in the order and post it.

  • No labels