Overview

The company creates production orders for remanufacturing for specific demand related to manufacturing of a product from its components.

The process is initiated when defects are identified in the product. The original product components are dismantled, automatically assigned to the production order, and consumed within the remanufacturing scenario.

Production orders can be used to create a schedule by items and quantity, control the order execution, and manage demand for production.

When the company creates a production order for remanufacturing, they need to specify a product to be remanufactured. The BOM outlines required operations and components. Default standard BOM and route sheets are specified for each remanufacturing product. Sometimes this data can be filled manually within production stages.

As a result of this process, a production order for remanufacturing is created.

Create production orders for remanufacturing flowchart

Create production orders for remanufacturing

(v.0)

Loading diagram...

Paths

PathManufacturing → Production scheduling and controlling → Production orders
In-app link EN code

e1cib/list/Document.ProductionOrder2_2

In-app link RU code

e1cib/list/Документ.ЗаказНаПроизводство2_2

How to create production orders for remanufacturing

Manually

1. Go to Manufacturing and then click Production orders under Production scheduling and controlling.

2. Click Create and select New.

3. In the Production order document, click the Main tab.

4. Select a Company and a Dispatching unit.

5. In the Type field, select Remanufacturing.

6. Select a Line of business if necessary.

7. Click the More tab.

8. Select a Person responsible.

9. Select the Separate supply of materials and works check box (recommended for the scenario) to track the material supply separately.

Plan-based production orders

See how to Generate plan-based production orders.

Demand-driven production orders

See how to Generate demand-driven production orders.

How to fill products for remanufacturing

1. In the Production order document, click the Remanufacturing products tab.

2. Click Add and fill the Item, Variant, and Quantity columns.

3. Select a product destination Warehouse for each line.

4. Fill the Assignment column if the product must be remanufactured under a certain order (a sales order, a repair order, and other).

5. At the bottom of the window, enter the Earliest start date for the production process. If no value is specified, the system will automatically use the current date as the production start date.

6. At the bottom of the window, enter the Requested completion date.

7. Select one of the Production scheduling options:

  • Backward to follow the ASAP ("as soon as possible") strategy.
  • Forward to follow the JIT ("just in time") strategy.

How to fill bills of materials

1. In the Production order document, click the Remanufacturing products tab.

2. Open the Bills of materials list and choose an option from the list.

3. Select a special BOM for the remanufacturing scenario.

Note

The remanufacturing scenario BOM includes:

  • The first recycling stage.
  • Subsequent manufacturing/kitting stages.

If necessary, send a request to the production master data manager.

How to save production orders

1. Set the Queued status.

2. Post the document.

The system will automatically:

  • Check if the required fields and their values are filled.
  • Indicate an error kind.
  • Provide recommendations on how to fix the error.